Short answer: Measure the footprint and calculate each material layer at its own finished depth. A surface refresh and a new layered drive are different orders; first record what is already on site.
Swipe the diagram sideways to see every label. The full calculation is written below it.
Sketch the full footprint
Split curves and widened parking areas into measurable shapes. The total surface area can be reused for each layer, but note any section where the depth or material changes.
Calculate layers separately
For each layer, calculate area × its own finished depth ÷ 324. A lower structural layer and an upper wearing layer may have different aggregate and densities. Combine totals only after you know how each will be sold.
Keep the products separate in one plan
Add one row for every distinct material in the gravel planner. Each row has its own density, allowance, and price. Add measured sections for depth zones and override any layer depth inside that section, including 0 if the layer is absent. Confirm the actual layer design with a local professional or supplier when drainage, weak ground, or vehicle loading is uncertain.
Hypothetical worked example
For a 720 sq ft footprint, a 3-inch top layer is 6.67 finished cubic yards and a 4-inch lower layer is 8.89 finished cubic yards. The combined finished depth is seven inches, but each product still needs its own density and purchase line.
Which situation matches your project?
Limit to check: Each material layer uses one supplier density and allowance across its sections. Separate materials still need separate layer rows, and a weak or wet area needs its own site design.
Measuring at the site? The guided field workflow records outlines and cutouts, checks their placement, and makes a printable sheet before you choose materials.
YardSetup prepared this guide from the stated geometry and the linked references where provided. The adjustable example runs in your browser. See our formulas and limits or report an error.