Short answer: Calculate the finished cubic yards of each layer from area and depth. Convert the planned order to short tons only with the selected aggregate’s bulk density and the quote’s sales unit.
Swipe the diagram sideways to see every label. The full calculation is written below it.
Find finished volume
Measure the driveway area in square feet and multiply by the intended finished depth in inches, then divide by 324. For example, 600 square feet at 3 inches is about 5.56 cubic yards before allowances.
Account for the order
If the finished layer will be compacted or material may be lost at the edges, add separately chosen allowances. Do not assume every supplier’s loose and compacted figures mean the same thing. YardSetup shows both the finished geometric volume and the order volume.
Convert with a real density
Multiply the order volume by the bulk density of the chosen product to estimate short tons. Ask your supplier for that density and for its truck capacity. The driveway planner accepts both, so its tonnage and load count reflect your quote.
Hypothetical worked example
A 600 sq ft layer at 3 inches is 5.56 finished cubic yards. With a 10% loose-material allowance and 5% handling allowance, the planning order is about 6.42 cubic yards. At 1.4 short tons per yard, that is about 9 short tons.
Which situation matches your project?
Limit to check: A published density table can be a rough comparison; use the actual supplier figure for an order.
Measuring at the site? The guided field workflow records outlines and cutouts, checks their placement, and makes a printable sheet before you choose materials.
YardSetup prepared this guide from the stated geometry and the linked references where provided. The adjustable example runs in your browser. See our formulas and limits or report an error.